Current Construction

Please see the Legend below for an explanation of the Schedule and Budget Health Indicators.

Project Name Current Estimated Project Cost Float to Milestone(s) Projected Over or Under-run Schedule Health Indicator Budget Health Indicator
1852 Columbia Parkway Sewer $5,570,000 276 days $920,000 GoodGood
Eastern & Delta Avenue - Phase 2 $14,720,000 1645 days $4,920,000 GoodGood
Mill Creek Wastewater Treatment Plant Preliminary Primary Improvements $49,660,000 88 days $11,760,000 GoodGood
Mill Creek Wastewater Treatment Plant Secondary Treatment System $58,400,000 400 days $19,900,000 GoodGood
Dry Run Sewers - Phases 1 and 2 $39,300,000 N/A $21,200,000 GoodGood
Little Miami Wastewater Treatment Plant Primary & Secondary Improvements $16,300,000 N/A $7,400,000 GoodGood
Health Indicator Legend
 Good Warning Critical
Schedule The available float to the 'complete construction' project milestone is in excess of one hundred eighty (180) calendar days. The available float to 'complete construction' milestone is in between one hundred and eighty (180) and ninety (90) calendar days or reduction of float has occurred in all of the past three (3) consecutive months. The available float to 'complete construction' milestone is less than ninety (90) calendar days and there is more than forty-five (45) calendar days of scheduled work remaining.
Budget The estimated project costs at completion are 95% or less of the WWIP budget.The estimated project costs at completion are between 95% and 100% of the WWIP budget.The estimated project costs at completion are in excess of the WWIP budget.
A program of the Metropolitan Sewer District of Greater Cincinnati