Sunset Avenues, Sunset Lane and Rapid Run Pike
- Completed in Spring 2017
- New storm sewers along Sunset Avenue, Rapid Run Pike, Sunset Lane, and Guerley Road
- One new stormwater detention basin off Sunset Lane
- Removes about 164 million gallons of stormwater from the combined sewer system during a typical year (when combined with the Rapid Run project).
- Conveys stormwater to the Lick Run Greenway from the roadways, Rapid Run Park bioswale and the Guerley Road detention dam.
Sunset Avenue Project Map:
Open cut construction along Sunset
Avenue at Guerley Road: